( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison

( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.(2017年下半年系统集成项目管理工程
A、The control accounts
B、Funding requirement
C、The cost estimates
D、The cost baseline






参考答案:D
参考解析: